The second phase of the Front Street Improvement Project starts. Crews begin demolition in the 300 block of Front Street (between Grace and Walnut Streets) on Wednesday September 21, pave the Grace Street intersection on Thursday, and plan to re-open Grace Street to traffic on Friday, September 23.
In the 200 block (between Chestnut and Grace Streets) the installation of underground water, sewer, and stormwater infrastructure is complete and crews are currently removing old and pouring new sidewalks, laying brick pavers and installing streetscape elements such as benches and lighting. The work in this block is scheduled for substantial completion by October 7 and re-open to full vehicle access shortly after.
The entire $3.5 million, two-block improvement project is slated for completion in November.